Upcoming Construction Activities
Sr. No | Activity | DIA (Inch) | Length (KM) | Commissioned On |
---|---|---|---|---|
1 | Hattar – Abbottabad Line | 16 | 62.50 | Procurement of Material / Acquisition of Land and Preparation of Design Drawings in progress |
2 | Mian Channun – Hasilpur Line | 12 | 90.00 | As above |
3 | Hasilpur – Chistaian Mandi Line | 8 | 35.00 | As above |
4 | Lachi – Manjuwala Line | 12 | 85.00 | As above |
5 | Hangu Line | 8 | 35.00 | As above |
6 | Manjuwala – End Point Line | 8 | 195.00 | As above |
Total | 502.05 | |||
Budgeted Cost (Million Rs) | 4200.00 |