Province-Wise Transmission Breakup

Province-Wise Breakup Transmission System as on 31-01-2022

Sr #. Section Dia Meter in Inches MainLine (KM) LoopLine (KM)
1PIRKOH - SUI24 70.50
2LOTI - PESHBOGI1811.25
3SUI - MULTAN2419.31
4SUI - MULTAN3019.31
SUB TOTAL BALOCHISTAN 101.06 19.31
Sr #. Section Dia Meter in Inches MainLine (KM) LoopLine (KM)
1SUI-MULTAN24 14.29
2SUI-MULTAN30 14.29
3SUI-MULTAN160.26
4GUDDU TPS42.41
5GUDDU BARRAGE241.81
6GUDDU CROSSING361.81
7SAWAN - QADIRPUR24131
8SAWAN CUSTODY TRANSFER POINT-SV1242.85
9SAWAN CUSTODY TRANSFER POINT- U/S OF SV1422.73
10SV1-SV2 LINE4225.12
11SV2 - SV4 SEGMENT4255.33
12SV4-SV54220.92
13SV5-QV1 SEGMENT42 29.40
14KAND KOT LINE1652.23
15QADIRPUR LINE3053.13
16QADIRPUR LINE3653.14
17QADIRPUR LINE (LNG PHASE-II)4253.14
18ENGRO FERTILIZER LINE 20 37.80
19ENGRO ENERGY LINE 16 3.30
20MARI DCPF - GENCO-II DEHYDRATION UNIT LINE12 4.50
21MARI DCPF - GENCO-II DEHYDRATION UNIT LINE10 5.50
SUB TOTAL SINDH309.08255.88
""
Sr #. Section Dia Meter in Inches MainLine (KM) LoopLine (KM)
1SUI - MULTAN18256.82
2SUI - MULTAN24288.06
3SUI - MULTAN30313.78
4SUI - MULTAN36213.68
5SUI - MULTAN161.85
6K1 – MP-37.882020.68
7SHER SHAH X-ING 36 2.20
8AC1X – AV7 (RYK)3626.96
9AC1X - AC2 (RLNG LINE)3644.62
10AC2 - AV9 (RLNG LINE)3618.52
11AV9 - AV10 (RLNG LINE)3620.78
12AV10 - A4 (RLNG LINE)36 30.1
13A4 - AC4 (RLNG LINE)3629.511
14AC4-AV15 (RLNG LINE)3625.348
15AV15 - AV-20 (RLNG LINE)365.74
16AV20 - AV 21 (RLNG LINE)3638.09
17AV21 - AV 22 (RLNG LINE)3627.79
18AV22 - AC6 (RLNG LINE)3627.35
19AC6 - AV29 (RLNG LINE)3623.16
20AV29 - N2 (RLNG LINE)2468.16
21N2 - SAHIWAL (RLNG LINE) 2477.296
22SAHIWAL - OKARA CANTT. (RLNG LINE)3024.25
23OKARA CANTT. - AKHTARABAD (RLNG LINE)3042.45
24AKHTARABAD - PHOOLNAGAR (RLNG LINE)3042.64
25AV17 - AV 20363.5
26AV21 – AV 223627.79
27SUTLEJ CROSSING - 1121.613.22
28SUTLEJ CROSSING - 2362.04
29KHANPUR LINE622.81
30A5 - BAHAWALPUR848.18
31AV22 - KOT ADDU1669.65
32AV22 - KOT ADDU2038.01
33MP 37.33 V/A - CMS KAPCO168.7
34 KOT ADDU - CHOWK SARWAR SHAHEED826
35D. G. KHAN LINE872.06
36DHODAK - KOT ADDU1677.79
37TPS MUZAFFARGARH LINE164.57
38QADIRPUR - AC-1X LINE3017.11
39QADIRPUR - AC-1X LINE3616.88
40QADIRPUR - AC-1X LINE (LNG PHASE-II)4217.13
41AHMEDPUR EAST618.34
42KHAN GARH822.2
43MULTAN - FERTILIZER LINE101.43
44JAHANIAN LINE830.49
45MULTAN - SIDHNAI1846.7
46MULTAN - SIDHNAI2422.4622.46
47MULTAN - SIDHNAI3046.701
48MULTAN - SIDHNAI3648.38
49AV29 - SAHIWAL36145.46
50A8-Ex AC7 (PUNJAB POWER PLANT LINE)2454
51Ex AC7 - END POINT (PUNJAB POWER PLANT LINE)2439
52KASHMORE-SHAHWALI LINE1220
53SHAHWALI-ROJHAN LINE (FIRST SEGMENT)124
54SHAHWALI-ROJHAN LINE (MP 14.92 TO MP 27.792)1221
55HAROONABAD LINE820
56SMS KHANGARH - KALLARWALI830
57SMS KALLARWALI - CHOWK PERMIT827.61
58SIDHNAI - FAISALABAD18163.58
59SIDHNAI - FAISALABAD2450.24
60SIDHNAI - FAISALABAD3053.29
61SIDHNAI - FAISALABAD3626.42
62SIDHNAI X-ING - AC-73633.26
63AC7 - HAVELI BAHADUR SHAH3037.3
64DARKHANA-SINDHELIANWALI LINE817.4
65T.T. SING - JHANG830.28
66DIJKOT-SAMUNDARY LINE822.33
67SAHIWAL - LAHORE18142.93
68SAHIWAL - AKHTARABAD2466.69
69SUNDER INDUSTRIAL STATE LINE164.34
70AC8 - SMSII (OLD)16 5.90
71AC8 - A11200.66
72WAPDA OFFTAKE FSD122.42
73CHAK JHUMRA LINE612.04
74FSD - MALIKWAL1219.34
75FSD - MALIKWAL16158.67
76FSD - MALIKWAL3090.82
77CV12A - KHATHIALA SHAKHAN LINE1228.23
78KATHIALA SHEIKHAN - MANDI BAHAUDDIN LINE129.1
79MANDI BAHAUDDIN - LALAMUSA LINE1247.17
80MALAKWAL - JHELUM CROSSING165.42
81CHENAB CROSSING CHINIOT181.13
82CHENAB CROSSING CHINIOT302.32
83KOT MOMIN - JOHARABAD (1)872.41
84KOT MOMIN - JOHARABAD (2)638.36
85JOHARABAD - CHASHMA882.21
86PIPLAN LINE817.05
87SARGODHA LINE1620.92
88CV3 (JHOKE MORE)-M3 INDUSTRIAL ESTATE LINE815.68
89FSD - SHAHDARA1657.48119.25
90NEW BV3 - MP 28.33 (RLNG LINE)16 25.10
91FSD - SHAHDARA2455.03
92BC1 - FAROOQ ABAD822.96
93SHAHDARA - LAHORE162.512.99
94RAVI CROSSING (1)160.58
95RAVI CROSSING (2)100.58
96SHAHDARA - WAPDA LAHORE103.41
97KHURRIANWALA - JARANWALA822.53
98DAWOOD HERCULES LINE125.87
99SHEIKHUPURA - GUJRANWALA (1)1059.44
100SHEIKHUPURA - GUJRANWALA (2)1644.57
101MP 59.91 - B3 LINE2422.83
102MP 59.91- TATLAYALI V/A (RLNG LINE)1644.57
103MP 59.91- BHIKHI POWER PLANT (QATPL)3016.17
104MP 59.91 - QUAID-E-AZAM APPAREL PARK16 17.00
105B2 - MP 50.70 (QATPL LINE)301.45
106MP 59.91 - NANDIPUR POWER PLANT 2476.4
107TATLAYALI V/A - MP 27.186 ON NANDIPUR POWER PLANT PIPELINE24 8.20
108B3-RAVI D/S LINE243.15
109KOTLI - RAHWALI (BV13)1830.76
110HAFIZABAD LINE843
111SHAHDARA - GUJRANWALA - RAHWALI1073.4
112RAHWALI - GUJRAT835.46
113RAHWALI - SIALKOT813.9713.97
114SIALKOT OFF-TAKE V/A TO PASROOR OFF-TAKE V/A1632.83
115RAHWALI-SIALKOT OFFTAKE181.48
116PASROOR - DHAMTAL - NAROWAL 840.55
117SIALKOT O/T - WAZIRABAD1820.25
118WAZIRABAD TO NEW D/S CHENAB RIVER X-ING V/A 166.57
119D/S RIVER CHENAB WAZIRABAD - JALALPUR JATTAN820
120SAHIWAL - LAHORE1676.67
121BSL U/S - BALLOKI POWER PLANT307.5
122PHOOL NAGAR - FEROZPUR ROAD2446.8
123PHOOL NAGAR - U/S HEAD BALLOKI1810.38
124D/S HEAD BALLOKI TO MP-59.911852.34
125PHOOL NAGAR - DAWOOD HERCULES1662.38
126PHOOLNAGAR - DAWOOD HERCULES2465.47
127U/S V/A HEAD BALLOKI TO D/S V/A HEAD BALLOKI (RLNG LINE)24 3.10
128ORIENT POWER PLANT LINE101.88
129SAPPHIRE POWER PLANT LINE100.22
130HALMORE POWER LINE123.4
131SAIF POWER PLANT SAHIWAL120.34
132GUJRAT - JHELUM854.27
133SARAI ALAMGIR - MIRPUR818.5
134RENALA-SATGARAH812.35
135MALIKWAL - HARANPUR - DANDOT121.18
136MALIKWAL - HARANPUR - DANDOT16 20.00
137CC1 - C43029.09
138C4 - CHAKWAL CEMENT10 24.00
139HARANPUR - GHARIBWAL813.02
140DANDOT - GALI JAGIR - WAH 1087.7
141DANDOT - GALI JAGIR - WAH 16153.51
142DANDOT - GALI JAGIR - WAH 3064.22
143DAKHNI - MEYAL - DHULIAN1650.44
144CV13a - CC1163.58
145RATANA LINE102.49
146SIL CROSSING101.46
147DHURNAL LINE (1)80.54
148DHURNAL LINE (2)1011.08
149DHULIAN - DAUDKHEL885.24.04
150FC1-MP 13.202421.25
151FC1-C6 PIPELINE FROM MID POINT VALVE ASSEBMLY TO END POINT C6 GALI JAGIR2418.901
152FC1-PINDIGHEB LINE2410.1
153MEYAL V/A - END POINT SMS PINDIGHEB2412.5
154KHUSHAL GARH BRIDGE-DAKHNI END POINT V/A2411.4
155POINT A V/A - SMS DHURNAL30.24
156GALI JAGIR - MORGAH (1)1021.43696
157GALI JAGIR - MORGAH (2)6 9.50
158GALI-RANIAL1635.57
159WAH - ISLAMABAD612.06
160WAH - HATTAR166.17
161WAH - HATTAR109.93
162ADHI - RAWAT10 47.70
163ADHI-SUKHO10 11.50
164RAWAT - MURREE1257.25
165BHANGALI LINE85.82
166MISSA KASWAL - MANDRA820.6
167WAH - NOWSHERA (1)1050.41
168WAH - NOWSHERA (2)16 52.60
169INDUS CROSSING241.12
170TAXILA LINE44.43
171SANJWAL LINE66.67
172KOHAT LINE811.58
173SHAKARDARA - DAUDKHEL1040.11
174DAUDKHEL-MIANWALI10 50.70
175MPCL (KALABAGH-1) - MID POINT V/A, MP 11.29 ON SHAKARDARA DAUDKHEL PIPELINE8 1.00
176SHAKARDARA END POINT - F310 1.55
177SADQAL - NAUGAZI LINE1619.02
178DASKA - PASROOR LINE824.86
179DASKA-SAMBRIAL LINE811.6
180FAUJI KABIR WALA LINE85.86
181OKARA - DIPALPUR LINE816.83
182ROUSCH POWER PLANT LINE16 4.70
183PINDORI - BHANGALI LINE815.83
184CV24-PINDORI (FIRST SEGMENT)1026.33
185KM 26.33 - KM 30.80 (CV24- PINDORI PIPELINE)104.47
186MIANWALI LINE8 17.80
187DI-KHAN BHAKAR LINE819.69
188MIAN CHUNNUN - HASILPUR1283.85
189HASILPUR - CHISHTIAN LINE830.98
190AV-40 - DIJKOT - TANDLIANWALA839.79
191AV-40 - BHAWANA LINE837.14
192SUKHO - RAWAT1636.24
193DIPALPUR - BASIRPUR822.64
194MANGA - PACKAGES LINE( RENTED POWER )836.65
195RODHO - KOT QAISRANI LINE12 14.50
196SAHIWAL -PHOOLNAGAR LOOP LINE FROM AKHTARABAD V/A to N-6 Pattoki V/A2420.95
197N-6 - PHOOL NAGAR O/T2421.69
198SHAHPUR-HUSSAIN SHAH LINE822.22
199HUSSAIN SHAH-SAHIWAL TOWN LINE813.52
200SAHIWAL TOWN-SILLANWALI LINE826.71
201RANDHAWA OFF-TAKE TO BADIANA8 8.50
202KOTLI RAI ABU BAKAR LINE87.05
SUB TOTAL PUNJAB 3341.31 3737.63
Sr #. Section Dia Meter in Inches MainLine (KM) LoopLine (KM)
1HATTAR-HARIPUR1018.12
2HATTAR OFFTAKE60.39
3HARIPUR-ABBOTTABAD852.53
4HARIPUR OFFTAKE81.53
5WAH-NOWSHERA(1)1025.13
6WAH-NOWSHERA(2)1623.68
7WAH - HATTAR1613.62
8HATTAR - SARAI SALEH1619
9HATTAR - HAVELLIAN16 15.00
10HAVILLINA - ABBATABAD1627.5
11C10 - ISMAILKOT1614.64
12KOHAT LINE8 19.20
13KOHAT - NOWSHERA 2485.52
14 ISMAILKOT - RASHKAI SPECIAL ECONOMIC ZONE 16   28.7
15MATANI - REGI LALMA8 32.50
16KOHAT-DAKHNI2443.32
17DHOKE HUSSAIN GAS FIELD-DHODA/KOHAT814.5
18EPF TOLANJ - GHORAZAI VALVE ASSEMBLY8 3.50
19MANZALAI - KOHAT LINE2439.01
20 JARMA - HANGO LINE8 36.00
21MUNJOWAL - BANNU836.5
22NOWSHERA-ISMAILKOT(1)811.97
23NOWSHERA-ISMAILKOT(2)611.97
24ISMAILKOT-TURNAB(1)820.85
25ISMAILKOT-TURNAB(2)620.86
26ISMAILKOT-TURNAB(3)1621.24
27SHAKARDARA - DAUDKHEL10 3.00
28KHARAPPA - SHAKARDARA8 25.50
29KHARAPPA - MANJOWAL1284.42
30NARI PANOOS LINE82.98
31MAKORI-KHARAPPA*108.75
32MUNJOWAL - PEZU853.29
33PEZU - D. I. Khan847.02
34PEZU - TANK831.51
35DI- KHAN BHAKAR8 18.80
36NOWSHERA-MDN-T.BAI-S/KOT857.99
37NOWSHERA-CHARSADDA823.59
38NOWSHERA - MARDAN1219.76
39MARDAN - SWAT12104.89
40 NOWSHERA - MARDAN162.16
41CHARSADDA-TURANG ZAI LINE610.36
42TANGI LINE613.87
43CHARSADHA - KHAZANA LINE822.64
44CHARSADHA - KHAZANA - DOLATPURA6 0.34
45JAHANGIRA - SWABI - TOPI 840.29
46JAHANGIRA - SWABI - TOPI 838.24
47JAHANGIRA OFF-TAKE - KABUL X-ING D/S162.52
48KABUL X-ING JAHANGIRA 16 0.30
49SAKHAKOT - SWAT8 68.06
50CHAKDARA-TALASH LINE831.6
51GURGURI - KOHAAT LINE10 78.00
SUB TOTAL KPK1019.56 407.09
 
AZAD KASHMIR
1SARAI ALAMGIR - MIRPUR817.35
SUB TOTAL AZAD KASHMIR17.35-
GRAND TOTAL (KM)   =   9208.27